CompFox Logo
AboutWorkflowFeaturesPricingCase LawInsights

Updated Daily

Case Law Database

Access over workers' compensation decisions, including En Banc, Significant Panel Decisions, and writ-denied cases.

Case No. MISSING
Regular Panel Decision

L&L Painting Co. v. Contract Dispute Resolution Board

L&L and Odyssey, contractors for lead-based paint removal on the Queensboro Bridge, disputed a contract drawing's interpretation with the Department of Transportation (DOT) concerning scaffolding clearance. Petitioners sought additional compensation after DOT rejected their proposed platform design, claiming a latent ambiguity in the contract. The Contract Dispute Resolution Board (CDRB) denied their claim, finding a patent ambiguity requiring pre-bid clarification. The Supreme Court upheld CDRB's decision, and this appellate court affirmed, concluding that the ambiguity was indeed patent, contrasting 'all roadways' in the note with the drawing's specific references. A dissenting opinion argued against this, stating an engineer would find no ambiguity.

Contract DisputePublic Works ContractQueensboro BridgeConstruction LawContract InterpretationAmbiguityPatent AmbiguityLatent AmbiguityCPLR Article 78Administrative Law
References
0
Case No. 2025 NY Slip Op 01159
Regular Panel Decision
Feb 27, 2025

Matter of American Bridge Co. v. Contract Dispute Resolution Bd. of the City of N.Y.

The Appellate Division, First Department, affirmed a lower court's decision denying American Bridge Company's (AB) petition to annul a determination by the Contract Dispute Resolution Board (CDRB). AB, a contractor for the New York City Department of Transportation (DOT), sought additional compensation for redesigning a protective shield on the Ed Koch Queensboro Bridge due to a discrepancy in vertical clearance measurements. However, the contract explicitly required AB to verify all existing dimensions, noting that DOT's figures were approximate. The court concluded that the contract unambiguously placed the responsibility for verifying dimensions on the contractor, and DOT had not made any bad faith misrepresentations, thereby affirming the denial of additional costs.

Contract DisputeConstruction ContractPublic WorksContract InterpretationRisk AllocationField MeasurementsBid DocumentsMisrepresentationAdministrative AppealArticle 78 Proceeding
References
4
Case No. MISSING
Regular Panel Decision

A&V 425 LLC Contracting Co. v. RFD 55th Street LLC

Plaintiff A&V 425 LLC Contracting Co. sought to foreclose upon 76 mechanic’s liens filed against condominium units and asserted claims for breach of contract and quasi-contractual remedies. The defendants, including RFD 55th Street LLC and individual unit owners, moved to discharge the liens and dismiss the causes of action. The court granted the motion to dismiss all four causes of action. The mechanic's liens were found invalid under Lien Law § 13 (5) as the deeds of conveyance to third-party purchasers contained the required trust fund provision and were recorded before the liens were filed. The breach of contract claim against non-parties was dismissed due to lack of privity and insufficient allegations for piercing the corporate veil. The quasi-contractual claims were also dismissed as a valid written contract existed covering the disputed subject matter.

Mechanic's LiensLien LawMotion to DismissBreach of ContractQuasi-ContractQuantum MeruitUnjust EnrichmentCorporate Veil PiercingPrivity of ContractConstruction Law
References
17
Case No. MISSING
Regular Panel Decision

In re the Arbitration between Lane & Leather Workers' Union of the United States

The case involves an appeal by an employer against a Special Term order compelling arbitration of disputes with a petitioner (union) following the expiration of a collective bargaining agreement. Disputes originated in January 1947 over roller wages, leading to a work stoppage in March that was settled by an agreement to arbitrate. A second dispute arose over the discharge of three employees, also demanded for arbitration. After the contract expired on June 1, 1947, the employer contended its obligation to arbitrate ceased. The Special Term ruled that the duty to arbitrate disputes arising during the contract term survived its expiration. The Appellate Division affirmed this order, specifying that arbitration should be limited to grievances pending before the contract's expiry on May 31, 1947.

ArbitrationCollective Bargaining AgreementWage DisputeWork StoppageEmployee DischargeContract ExpirationArbitrabilityAppellate ReviewLabor LawPanel Decision
References
6
Case No. MISSING
Regular Panel Decision
Jun 04, 2007

FCI Group, Inc. v. City of New York

This case involves an action brought by a contractor against the City of New York and the Department of Citywide Administrative Services (DCAS) for the balance due on a construction contract. The defendants contended that the plaintiff forfeited its right to further payment due to the attempted bribery of two city employees by the plaintiff's president. The Supreme Court initially denied the defendants' motion for summary judgment, but this Court reversed that decision. It found that the contract's narrow alternative dispute resolution clause was inapplicable to the dispute. Crucially, the Court concluded that the plaintiff was bound by the contract’s forfeiture provision and that its enforcement did not offend public policy, as the unlawful conduct was central to the performance of the contract, thereby barring recovery.

Construction ContractContract ForfeitureBriberyPublic PolicyAlternative Dispute Resolution (ADR)Summary JudgmentUnlawful GratuitiesEthical ConductContract InterpretationNew York City Charter
References
28
Case No. MISSING
Regular Panel Decision

Microtech Contracting Corp. v. Mason Tenders District Council of Greater New York

Plaintiff Microtech Contracting Corporation sought a preliminary injunction to stop defendants, including the Mason Tenders District Council and Local 78, from displaying an inflatable rat at its work sites. Microtech argued this conduct violated a 'no-strike' provision in their collective bargaining agreement (CBA). The District Court denied the motion, citing a lack of jurisdiction under the Norris-LaGuardia Act because the underlying labor dispute was not subject to mandatory arbitration as per the CBA. The court also held that Section 104 of the Act specifically prohibits injunctions against publicizing labor disputes by non-fraudulent or non-violent means. Furthermore, the court determined that even if jurisdiction existed, the use of the inflatable rat was protected First Amendment speech and did not fall under the 'disruptive activity' clause of the CBA, which was interpreted to apply only to actions similar to work stoppages.

labor disputepreliminary injunctionNorris-LaGuardia Actcollective bargaining agreementFirst Amendmentinflatable ratunion protestno-strike clausearbitrabilityjurisdiction
References
22
Case No. MISSING
Regular Panel Decision

McSpedon v. Profile Electric, Inc.

The petitioner, Local Union No. 3, International Brotherhood of Electrical Workers, AFL-CIO, appealed an order from the Supreme Court, Queens County, dated April 29, 1987. The order had denied the union's motion to stay arbitration and granted Profile Electric, Inc.'s cross-motion to compel arbitration. The dispute arose under a collective bargaining agreement where Profile Electric alleged the union failed to provide sufficient qualified labor, hindering a city contract. The Supreme Court, and subsequently the appellate court, determined that given a broad arbitration clause, the dispute fell within the contract's ambit, emphasizing the state's policy favoring arbitration. The appellate court affirmed the decision, holding that the merits of the claim and issues of contract termination were matters for the arbitrators.

ArbitrationCollective Bargaining AgreementLabor DisputeStay ArbitrationCompel ArbitrationAppellate ReviewContract InterpretationUnion ObligationsEmployer-Union RelationsQueens County
References
3
Case No. MISSING
Regular Panel Decision
Aug 16, 2006

Superior Ice Rink, Inc. v. Nescon Contracting Corp.

The plaintiff contracted with Nescon Contracting Corp. for painting services and required to be named an additional insured under Nescon's liability policy. Nescon's insurance broker, Seigerman-Mulvey Company, Inc., issued a certificate indicating plaintiff was an additional insured, but the insurer, Merchants Mutual Insurance Company, later disclaimed coverage after workers were injured on the plaintiff's premises. The plaintiff sued Seigerman-Mulvey for breach of contract, alleging third-party beneficiary status. The Supreme Court denied Seigerman-Mulvey's motion to dismiss the complaint. However, the appellate court reversed, granting the motion to dismiss, holding that the plaintiff was not in privity of contract with Seigerman-Mulvey, was owed no duty by them, and failed to establish itself as an intended third-party beneficiary or demonstrate fraud, collusion, or other special circumstances for recovery.

Breach of ContractInsurance Broker LiabilityThird-Party BeneficiaryMotion to DismissAdditional InsuredPrivity of ContractAppellate ReviewInsurance Coverage DisclaimerCPLR 3211(a)(7)Pecuniary Loss
References
4
Case No. 2014 NY Slip Op 05293 [119 AD3d 718]
Regular Panel Decision
Jul 16, 2014

Caiazzo v. Mark Joseph Contracting, Inc.

Ronald Caiazzo, Jr. sued Mark Joseph Contracting, Inc., Julia Coen, and Ana Reyes for personal injuries sustained while installing an air conditioning system at a house owned by Julia Coen. Caiazzo fell from a makeshift step, alleging violations of Labor Law §§ 200, 240(1), 241(6) and common-law negligence. The Supreme Court initially granted summary judgment dismissing certain claims. On appeal, the Appellate Division affirmed the dismissal of Labor Law §§ 200, 240(1), and 241(6) claims against Mark Joseph Contracting, Inc., and Labor Law §§ 240(1) and 241(6) claims against Julia Coen, citing the homeowner exemption for Coen. However, the court reversed the denial of summary judgment to Mark Joseph Contracting, Inc. on the common-law negligence claim, granting dismissal. The denial of summary judgment for Julia Coen on Labor Law § 200 and common-law negligence was affirmed, as triable issues of fact remained regarding her notice of a dangerous condition.

Personal InjuryLabor LawConstruction SiteSummary JudgmentCommon-law NegligenceElevated Work SiteDangerous ConditionHomeowner ExemptionAppellate ReviewSuffolk County
References
25
Case No. action No. 2
Regular Panel Decision

U.W. Marx, Inc. v. Koko Contracting, Inc.

Koko Contracting, Inc., a subcontractor, ceased work on a school construction project after U.W. Marx, Inc., the general contractor, failed to make three successive progress payments. Marx declared Koko in default and terminated the contract. In action No. 2, the Supreme Court found in favor of Koko, ruling that Marx's failure to pay was a material breach of contract. Marx and its surety, Continental Casualty Company, appealed, arguing Koko's recovery was precluded by its failure to provide seven days' written notice before suspending work as required by the subcontract. The appellate court affirmed the lower court's decision, holding that Marx's prior material breach relieved Koko from its obligation to strictly comply with the notice provision, as the clause was primarily for the subcontractor's benefit regarding remobilization costs.

Construction ContractMaterial BreachNonpaymentSubcontractorGeneral ContractorAppealNotice to CureSuspension of WorkContract PerformanceContractual Obligations
References
9
Showing 1-10 of 4,650 results

Ready to streamline your practice?

Apply these legal strategies instantly. CompFox helps you find decisions, analyze reports, and draft pleadings in minutes.

CompFox Logo

The AI standard for workers' compensation professionals. Faster research, deeper analysis, better outcomes.

Product

  • Platform
  • Workflow
  • Features
  • Pricing

Solutions

  • Defense Firms
  • Applicants' Attorneys
  • Insurance carriers
  • Medical Providers

Company

  • About
  • Insights
  • Case Law

Legal

  • Privacy
  • Terms
  • Trust
  • Cookies
  • Subscription

© 2026 CompFox Inc. All rights reserved.

Systems Operational